2025–26 Departmental Results Report – Supplementary Information Tables – Regulatory and Permitting Efficiency for Clean Growth Projects
The Cabinet Directive on Regulatory and Permitting Efficiency for Clean Growth Projects focuses on the federal efforts needed to accelerate regulatory efficiency for clean growth projects. It is intended to help get clean growth projects built faster by accelerating decision-making related to these projects.
Section 1. Overview of the Canada Energy Regulator’s Role in Supporting Regulatory and Permitting Efficiency
Making decisions or recommendations to the Governor in Council on applications, which include impact assessments, using processes that are fair, transparent, timely and accessible. These applications pertain to pipelines and related facilities, international power lines, offshore renewable energy, tolls and tariffs, compensation disputes resolution, energy exports and imports, and oil and gas exploration and drilling in certain northern and offshore areas of Canada.
Section 2. Results for Thematic Areas of the Cabinet Directive
The Canadian Energy Regulator Act (CER Act) establishes the Commission of the Canada Energy Regulator and sets its mandate to exercise adjudicative functions in an independent manner. The Commission decides these matters in a predictable and timely manner to provide certainty to investors and stakeholders, drive innovation and support sound projects that create jobs for, and provide energy to, Canadians.
Theme 1: Strengthening service standards
Actual Results:
Since 2019, the CER has met its legislated time limits for infrastructure project reviews 99 per cent of the time, with no missed time limits since the 2020-21 reporting period. The CER has also met service standards 92 per cent of the time since the 2020-21 fiscal year.
During 2025-26, the Commission released 925 decisions on applications related to infrastructure, tolls and tariffs, export licences and orders, frontier exploration and production, leave to open orders and other matters that spanned the energy infrastructure lifecycle. The Commission processed all applications within the CER Act legislated time limits.
The Commission strives to exceed time limits by setting service standards that define shorter time limits for certain types of applications. For applications under section 214 of the CER Act, decisions were released within the service standards of 40, 90 or 120 days instead of the 130, 210 or 300 days mandated in time limits. In 2025-26, the CER met the Service Standards 83 per cent of the time for applications for which a service standard applied.
This past fiscal year, the Commission continued its focus on increasing the efficiency of section 214 completeness determinations. Having instituted a 30-day internal service standard, the Commission is now averaging 28 days for completeness determinations. That means routine applications proceed more quickly to assessment. In addition, the overall assessment time for such applications has been reduced to an average of 90 days in 2025-26, down from 127 days in 2023-24 - an improvement of nearly 30 percent.
This past fiscal year, the Commission of the CER issued Certificates for two pipelines under section 183 of the CER Act (large pipeline projects). The Commission completed its review of Westcoast Energy Inc.’s application for the Sunrise Expansion Program in 437 days, and Pouce Coupé’s Taylor to Gordondale Pipeline Project in 406 days – both within the legislated time limit of 450 days. Since the CER Act came into force, the Commission has averaged 421 days to review large pipeline projects.
Since the CER Act came into force, no Commission decisions have been overturned by a higher court, illustrating the strength and robustness of Commission assessments and decisions. This provides certainty to investors and stakeholders, drives innovation and enables the carrying out of sound projects that create jobs for Canadians.
In Spring 2025, the CER launched the Regulatory Optimization Process (ROP) to identify and implement opportunities to enhance adjudicative efficiency and strengthen regulatory processes. Under the ROP, the CER made a number of changes to improve regulatory efficiency, including standardizing early steps for larger applications for which a hearing would be held and making completeness determinations clearer and more transparent, and clarifying how Crown Consultation is done for smaller pipeline applications.
Effective December 1, 2025, the CER introduced new Streamlining and Decommissioning Exemption Orders following a public engagement period. These Orders, replacing the previous versions under the National Energy Board Act, make the approval process for negligible-risk oil and gas projects more efficient and predictable by reducing unnecessary requirements and improving clarity.
| Departmental Result Indicator | Target | Date to achieve target | Actual Result |
|---|---|---|---|
| Percentage of adjudication decisions and recommendations that are made within legislated time limits and service standards. | Exactly 100% | March 2026 | 2023-24: 100% 2024-25: 100% 2025-26: 83%(a) |
|
(a) The service standards aspect of this indicator did not meet the target. Specifically, the 12-week service standard for issuing a Recommendation report following the close of record was delayed by 10 calendar days for the Pouce Coupé Pipe Line Ltd. Taylor to Gordondale Pipeline Project. The time limits aspect of this indicator was met for the year. This indicator is an aggregated metric; one missed service standard milestone in a single category disproportionately lowered the overall result, despite meeting legislated time limits (100%) and service standards (99%) overall. |
|||
The CER has Memoranda of Understanding (MOUs) with Environment and Climate Change Canada, Fisheries and Oceans Canada (DFO), Natural Resources Canada and Transport Canada. The CER also has MOUs with other federal, territorial and provincial boards and agencies for specific purposes. In 2025-26, the CER and Environment and Climate Change Canada added Operational Annexes to the MOU to specifically address Compliance and Enforcement and Environmental Emergency Management.
The MOU between the CER and DFO is specifically about authorizations under the Fisheries Act. The CER is responsible for reviewing any work, undertaking, or activity within the CER’s jurisdiction against the Fisheries Act and Species at Risk Act, and refer anything to DFO that may require authorization or permitting. This past fiscal year, CER staff reviewed five applications (228 crossings). Staff referred to DFO for additional review seven of those 228 crossings for site-specific review. Staff also reviewed 59 Operations & Maintenance activities (79 crossings) and referred 13 to DFO for additional review.
The CER encourages federal authorities to rely on the engagement records provided in the CER’s regulatory processes to enhance permitting efficiency and timeliness.
Theme 2: Providing timely guidance to proponents
Actual Results:
The Commission has a broad mandate under the CER Act and may consider matters that appear to the Commission to be directly related to the pipeline and relevant to its decisions or recommendations. The Commission is responsible for assessing, among other things, the environmental and socio-economic effects of energy projects within its jurisdiction. The CER Act outlines the factors that the Commission must consider when making a decision or recommendation for certain projects, including pipeline and powerline projects. In particular, a factor that the Commission must take into account is the consideration of environmental obligations and the Government of Canada’s climate change commitments.
The CER’s Filing Manual outlines the Commission’s expectations on what information should be included in an application for a potential project and is based on the factors identified in the CER Act. The CER’s Filing Manual provides guidance on the biophysical, economic and financial, technical and socio-economic elements that should be considered by a proponent in developing an application. The CER updates various sections of its Filing Manuals on a regular and ongoing basis to reflect changing requirements, conditions, regulations, industry practices, and feedback received from regulated companies, Indigenous Peoples and other interested persons or groups in support of a transparent and efficient process for applicants and participants.
In 2025-26, the CER continued to update the Environmental and Socioeconomic Assessment (Guide A.2) and Lands (Guide A.4) sections of the Filing Manual. An extensive public engagement period was concluded to review these sections, in conjunction with the CER’s Onshore Pipeline Regulations Review. Improvements to the filing guidance will be informed by 110 written submissions received on 13 topic-specific discussion papers, as well as 116 engagements (including information sessions and workshops with industry, Indigenous communities and other interested parties). The updated sections are expected to be available in fall 2026.
Theme 3: Coordinating consultation with Indigenous Peoples
Actual Results:
Crown consultation on energy projects regulated under the CER Act, occurs primarily through the Commission’s assessment process. The Commission has the technical expertise and mandate to consider and address project impacts, including those affecting the rights and interests of Indigenous Peoples. For this reason, Indigenous Peoples are encouraged to participate directly in the Commission’s process to identify issues, concerns, or potential mitigation measures with respect to potential impacts of a proposed project. The Commission provides opportunities for Indigenous Peoples to fully participate in its regulatory hearing processes and share their views about a proposed project. This includes through written submissions as well as sharing Indigenous knowledge orally, and if requested, confidentially to inform the Commission’s deliberations on a project.
For certain applications, typically those that require a decision by the Governor in Council, the CER may conduct additional Crown consultation activities with potentially impacted Indigenous communities to supplement and complement the Commission’s process. These activities are carried out by the CER in its role as the Crown Consultation Coordinator (CCC). The CCC works directly with potentially impacted Indigenous communities on an individual community basis as well as through multi-party workshops or meetings and reports information and recommendations on the record to the Commission for consideration in their assessment. To date, the CER has conducted these activities for proposed project applications filed with the CER under section 183 of the CER Act. In this fiscal year, this included the Pouce Coupé Pipe Line Ltd. Taylor to Gordondale Pipeline Project (T2G Project) in Alberta and British Columbia and the Westcoast Energy Inc. Sunrise Expansion Program (Sunrise Project) in British Columbia.
In 2025-2026, the CCC conducted supplementary Crown consultation with 107 Indigenous communities regarding the Sunrise Project and T2G Project. The CCC works to align with the UN Declaration in its consultation activities. As a result of these consultations, the CCC provided information on the concerns and potential impacts of the Projects identified by Indigenous communities through its submissions on the Commission’s hearing record. The direct dialogue with Indigenous communities informed the Commission’s assessment, resulting in additional conditions and accommodations to better address potential impacts and concerns raised by Indigenous communities involved on the Project. As part of its consultations, the CCC sought information related to Free, Prior, and Informed Consent (FPIC) for the Projects, and to understand what steps Indigenous communities may take to work towards achieving consent. This information, when available, was provided to the Commission and the Governor in Council for decision making. Ultimately, both Projects were recommended for Approval and Certificates were issued within legislated timeframes.
Coordinate Crown consultations with other regulatory departments
The CCC also coordinates Crown consultation with federal and provincial government departments through working groups. This work supports process efficiency and a whole of government response to concerns and potential impacts identified by Indigenous communities, as appropriate, when informing the Commission and/or Governor in Council. The CCC’s whole-of-government approach includes regular meetings with other federal departments, territories and/or provinces to provide updates on discussions with Indigenous communities, to discuss information on impacts to rights or concerns raised by Indigenous communities and may include joint meetings with Indigenous communities. Where potential topics or concerns raised by Indigenous communities are within another department’s mandate or expertise, the CCC seeks input from that department to include in submissions to the Commission and/or the Minister of Energy and Natural Resources to support a Governor in Council decision on projects. For example, on the Sunrise Expansion Project, the CCC coordinated the participation of Indigenous Services Canada, Crown-Indigenous Relations and Northern Affairs Canada, Environment and Climate Change Canada, and the province of British Columbia with regards to sensitive issues arising from pipeline crossings on reserve and requests for solutions that require longer term whole-of-government responses.
Increase practice of early engagement ensure actions align with the United Nations Declaration on the Rights of the Indigenous Peoples.
Since 2019, the CER’s increased early engagement practices have been designed to align with the articles of the United Nations Declaration on the Rights of Indigenous Peoples. The CER’s Early Engagement Guide provides proponents with the CER’s expectations, including filing requirements, guidance and expectations for engagement with Indigenous communities during the Early Engagement Phase for projects within the CER’s jurisdiction. On certain applications, the CCC conducts engagement with Proponents and Indigenous communities to build meaningful relationships, to support open dialogue, and the early identification of potential impacts and concerns related to a project, consistent with the articles of the United Nations Declaration on the Rights of the Indigenous Peoples. When the CCC conducts early engagement, it presents its findings to the Commission on the record to inform its assessment. While early engagement activities did not occur this fiscal year, topics raised with the CCC during the Early Engagement Phase on both the T2G and Sunrise Projects remained relevant throughout the entire hearing process and influenced final conditions within the Commission’s recommendation.